Case Study: Sherburn Bears Rugby Club
Project: Refurbishment of the existing club and the building of a one-storey extension
Client: Sherburn Council
Value: £113,500.00
Pre-Construction Phase – QS services, Tender Review
Construction Phase – Post Contract. RIBA stages 2-7
Cooper & Hall was awarded the contract in February 2019. A competitive field of applicants was narrowed down in an initial single stage tender process. The contractor was selected using weighted, pre-defined parameters which held particular importance for the client.
A JCT 2016 Intermediate building contract was negotiated which evenly and fairly distributed the allocation of risk between employer and contractor and works began in March 2020.
Progress was halted by COVID-19, starting again in June 2020 and finishing four months later. Disruption caused to suppliers by the pandemic were overcome through good communication, diligent programming and hard work.
The complete restoration of Grade II listed Liverpool Library, one of the UK’s biggest library developments.
Construction of an award-winning, innovative new build school.
Alteration and extension of the existing operational shopping centre.