Case Study: Riverside House Cat A and B fit out


Case Study: Riverside House

Project: CAT A and B fit out of ground, 1st and 2nd floor offices plus external works

Client:  Bailie Group

Value: £1.2m

Service Provided:

Pre-Construction – Contract Advice and Risk Assessment

Construction Phase – Commercial Management, Contract Administration and Project Reporting

 

In June 2020, Cooper & Hall were approached by the Bailie Group to act as Employers’ Agent, and to carry out commercial management, contract administration and project reporting duties on the comprehensive fit out of their 10,000 sq ft office development in Canal Wharf, Leeds.

On review of the draft contract proposed by the contractor, C&H advised Bailie Group that a number of alterations may be prudent to distribute risk more evenly between the client and the contractor. The changes were proposed to the contractor, detailing the reasoning and basis for each and a contract was agreed shortly after.

As with many projects at this time, progress was halted by COVID-19 in March 2020, starting again in June of that year, finishing four months later in October. A co-operative working environment was fostered through site visits, good communication and an open relationship with all parties.

C&H’s commercial management and project reporting showed the client progress on a weekly basis, while pre-contract risk assessment provided protection from risk; start through to completion. This gave the client peace of mind and the confidence of a successful project.

Similar Projects


CH---Liverpool-Library

Liverpool Library

The complete restoration of Grade II listed Liverpool Library, one of the UK’s biggest library developments.

>>>Learn More

CH---Sports-College

Sports College, Monkseaton

Construction of an award-winning, innovative new build school.

>>>Learn More

CH---The-Mall

The Mall, Blackburn

Alteration and extension of the existing operational shopping centre.

>>>Learn More